INDUSTRIAL DRYER IMPLOSION, RURAL WALES

Capacity: CONTRACTS MANAGER

 

Overall Project responsibility for new powder drying facility following industrial. implosion.

£40M Overall project value.

Refurb project with existing leaning in steel structure, highly complex jacking and pulling works to straighten existing frame and new build twixt two existing live processing Foodsafe structures.

Principle Contractor and Principal Designer capacity.

Commercial protection of all parties to include working under client insurance stakeholders and facility owners.

Multiple hazard site working in live processing Foodsafe conditions.

Highest level of permit systems, H&SE and client interface issues resolved daily.

Specialist transport – floating barge of larger items too large to transport via road, international shipping requirements.

Highly technical groundworks to take superstructure loadings.

Specialist metallurgy of structure to processing interface to limit bimetallic corrosion.

Technical review and Managerial responsibility for all aspects of Design & DO activities, Fabrication Depts. Procurement & Logistics, Heavy Lift, Site Installation, Site Welding Activities, Protective Coatings etc.

Conduction of all Client/Engineer/Sub Contractor meetings and overall Project Coordination for all activities.

Specialist access solutions found for a challenging WAH environment.